Lawsuit: Ida outages due to 'gum and super glue' at utility

Lawsuit: Ida outages due to 'gum and super glue' at utility

SeattlePI.com

Published

NEW ORLEANS (AP) — A lawsuit alleges that Louisiana's largest electric utility used a “bubble gum and super glue” approach to maintenance and construction that left customers sweltering in the dark without adequate sewage treatment after Hurricane Ida.

The suit was filed Saturday against Entergy Corp. and its subsidiaries Entergy Louisiana and Entergy New Orleans. Entergy has said about 902,000 customers lost power after the major hurricane made landfall on Aug. 29.

Entergy's website indicated that about 22,200 users were without power Monday, nearly 11,500 of them in Lafourche Parish, which Ida hit with sustained winds of up to 150 mph (240 kph).

Entergy does not comment on pending litigation, corporate spokesman Neal Kirby said in an email Monday.

The suit seeks to represent everyone who lost power, and Judge Rachel Johnson will decide whether to certify it as a class action claim.

“Before Hurricane Ida hit Southeast Louisiana, it was Entergy’s position that its systems which provided power to 1.1 million residents and businesses, could withstand winds of 150 mph" but a number of studies had indicated otherwise, the lawsuit said.

Although climate change is bringing more frequent and intense hurricanes, it added that “grossly inadequate maintenance and inspection,” antiquated equipment, and shoddy maintenance “created a system that could not and would not sustain even a hurricane with wind gusts below 100 miles per hour” (160 kilometers per hour).

That included peak gusts of 90 mph (145 kph) in New Orleans and at its international airport in suburban Kenner, the lawsuit said.

Underground cables would have protected power transmission in southeast Louisiana, the lawsuit said. “Instead, Entergy chose the bubble gum and super glue approach to protect their billions of...