NJ offshore wind to connect at 2 former power plants onshore

NJ offshore wind to connect at 2 former power plants onshore

SeattlePI.com

Published

ATLANTIC CITY. N.J. (AP) — A large offshore wind energy project planned off the coast of New Jersey will connect onshore to two former power plants, and cables will run under two of the state's most popular beaches, officials said Tuesday.

At a virtual public hearing on the Ocean Wind project planned by Orsted, the Danish wind energy developer, and PSEG, a New Jersey utility company, officials revealed that the project would connect to the electric grid at decommissioned power plants in Ocean and Cape May Counties.

The northern connection would be at the former Oyster Creek nuclear power plant in Lacey Township; the southern connection would be at the former B.L. England plant in Upper Township.

Cables running from the wind farm, to be located between 15 and 27 miles (24 to 43 kilometers) off the coast of Atlantic City, would come ashore at one of three potential locations in Ocean City: 5th Street, 13th Street or 35th Street. They would then run under the roadway along Roosevelt Boulevard out to Upper Township and the former power plant, which closed in 2019.

Cables also would need to cross Island Beach State Park in Ocean County, running under the dunes and beach and existing parking lots, out into Barnegat Bay, coming ashore either directly at the Oyster Creek site in the Forked River section of Lacey, or at either Bay Parkway or Lighthouse Drive in Waretown, also known as Ocean Township in Ocean County.

Pilar Patterson, permit manager for Orsted, said the onshore work in beach areas would be kept to a minimum during the summer.

She said the company had done visualization studies showing that it would be difficult for the average person to see the windmill turbines from the shoreline, noting that weather conditions, time of day and other factors all affect...