Quarterly Activities for the Period Ended 30 June 2020

Quarterly Activities for the Period Ended 30 June 2020

GlobeNewswire

Published

TORONTO, Aug. 03, 2020 (GLOBE NEWSWIRE) -- *Cardinal Resources Limited *(ASX: CDV; TSX: CDV) (“*Cardinal” *or “*the Company”*) a Ghana gold focused exploration and development company, is pleased to present its Quarterly activities report for the period ended 30 June 2020.

**HIGHLIGHTS**

· On March 16, 2020 the Company advised that it had received notification from Nord Gold SE (Nordgold) that it had acquired a relevant interest of 19.9% of the shares in Cardinal, (having acquired 16.4% stake previously owned by Goldfields Limited), and further advised that Nordgold had provided a non-binding indicative and conditional proposal to acquire all the issued capital of Cardinal that it did not already own for AU$0.45775 per share in cash.· On March 30, 2020 the Company updated its shareholders and provided commentary as to how the Company is managing the current COVID-19 pandemic.· On May 4, 2020 the Company announced an update on permitting approvals and COVID-19 impacts on the Company’s progress.· On June 5, 2020 the Company announced that the senior secured credit facility (as amended in February 2020 and March 2020) had been assigned from Sprott Private Resource Lending, L.P. to the Ghana Infrastructure Investment Fund (GIIF), a Ghana Government owned infrastructure investment vehicle.· On June 16, 2020 the Company responded to media speculation in Ghana and advised that the Company continued strategic discussions with banks, financiers and other parties which continued to show interest in bringing the Namdini Project into production with a view to maximising economic outcomes. Whilst discussions in relation to any potential transaction remain ongoing, at that time no agreement had been entered into in relation to any transaction.· On June 18, 2020 the Company announced the recommended all-cash takeover offer of Cardinal Resources by Shandong Gold Mining (Hong Kong) Co, Ltd (a subsidiary of Shandong Gold Mining Co, Ltd) (“Shandong Gold”). Cardinal entered into a Bid Implementation Agreement with Shandong Gold, pursuant to which Shandong Gold agreed to acquire 100% of the issued and outstanding ordinary shares in Cardinal at a price of AU$0.60. Proposed implementation by way of an off-market takeover offer with a 50.1% minimum acceptance condition. The Board of Cardinal unanimously recommended acceptance of the Shandong Gold offer in the absence of a superior proposal.· On July 7, 2020 the Company announced that it had raised AU$11,960,000 as a result of the issue of 26,000,000 fully paid ordinary shares to Shandong Gold in accordance with the terms of the Bid Implementation Agreement.· On July 15, 2020 Cardinal received an unconditional on-market takeover offer at AU$0.66 per share from Nordgold. Having regards to the unsolicited nature of the takeover bid and the provisions of the Bid Implementation Agreement with Shandong Gold, the Board of Cardinal recommended a ‘take no action’ at the time in relation to the Nordgold takeover bid.· On July 20, 2020 the Company advised that its Namdini Mining Licence had officially received Sovereign Parliamentary Ratification in Ghana.· On July 22, 2020 the Company advised that it had received a revised and improved proposal for an off-market takeover from Shandong Gold, pursuant to which Shandong Gold will offer to acquire all of the shares in Cardinal it does not presently own at a cash price of $0.70 per share.· On July 27, 2020 the Company, after careful consideration of the Revised Shandong Gold Offer and Nordgold’s unconditional on-market offer for Cardinal, Cardinal’s Board of Directors (in consultation with the Special Committee, its financial and legal advisors), unanimously recommended that Cardinal shareholders

· *ACCEPT *the Revised Shandong Gold Offer (in the absence of a superior proposal); and

· *REJECT *the Nordgold Bid.

· On July 30, 2020 the Company advised that it had entered into a deed with each Shandong Gold Mining (HongKong) Co., Limited and Shandong Gold Mining Co., Ltd, to amend the Bid Implementation Agreement.

**OUTLOOK**

The principal activity of the Company is gold exploration and mine development in Ghana. The Company holds tenements prospective for gold mineralisation in Ghana in two granite‐greenstone belts: the Bolgatanga Project and the Namdini Gold Project (“Namdini”), which are, respectively, located within the Greenstone Belts in northeast Ghana and the Subranum Project, which is located within the Sefwi Greenstone Belt in southwest Ghana.

The main focus of activity is the Namdini Gold Project which has a gold Ore Reserve of *5.1Moz* (138.6Mt @ 1.13g/t Au; 0.5g/t Au cut‐off) inclusive of 0.4Moz Proved (7.4Mt @ 1.31g/t Au; 0.5 g/t Au cut‐off) and 4.7Moz Probable (131.2Mt @ 1.12 g/t Au; 0.5g/t Au cut‐off).

In response to the COVID-19 pandemic and following advice from the World Health Organization (“WHO”) as well as the Australian, Ghanaian, and Canadian Governments, Cardinal has enacted changes to its exploration programme and on-site development programme, primarily focused on the safety and well-being of our workforce.

All international travel remains suspended.  On the ground in Ghana, the workforce has been reduced to key personnel only. According to WHO External Situation Report 189 (July 27, 2020), there had been 32,435 confirmed cases of COVID-19 in Ghana, including cases via local transmission. 161 deaths from COVID-19 have been recorded in Ghana at the time of this report.  At the time of writing, the Northern Region of Ghana, where Cardinal’s main tenements are located, have recorded 308 COVID-19 cases with one death. Some restrictions and lockdowns have been eased. Strict COVID-19 Operational Procedures have been introduced on site and in Cardinal Offices in Perth and Accra.

The Company is doing everything to ensure it is well placed to resume normal business as soon as practically possible. The Project technical team and its partners are still actively working on adding value to the Namdini Gold Project.

Figure 1 accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/b24c0235-c0a9-47cd-9c17-337d1fe65ec4

*THE NAMDINI GOLD PROJECT*

Property Title / Mining Lease

A Large‐Scale Mining License covering the Namdini Mining Lease was granted to Cardinal Namdini Mining Limited (“*Cardinal Namdini”*), a wholly owned subsidiary of Cardinal, by the Minister of Lands and Natural Resources (“*the Minister*”) under the Ghanaian Minerals and Mining Act 2006 (Act 703) (“the Act”) in December 2017.

In February 2020, the Minister - in accordance with the Act- approved the application to expand the original Mining Lease to the maximum allowable area. The expanded Large-Scale Mining Lease now totals 63km^2 and is valid for a renewable term of 15 years from 2020 (Figure 2).

Subsequent to the Quarter end the Company advised that its Namdini Mining Licence had officially received Sovereign Parliamentary Ratification in Ghana.

Figure 2 accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/5e9be1ee-7974-4933-bf9b-4bd1f133d111

***7.4Mt @ 1.31g/t Au for 0.4Moz Au Proved and 131.2Mt @ 1.12g/t Au for 4.7Moz Au Probable; 0.5g/t Au cut‐off

*Project Development Timeline*

*Table 1: Proposed Project development schedule (Subject to Financing and COVID-19 impact).*

*Milestone* *Target timeline*
*Advance Front End Engineering and Design (“FEED”) to completion* Q4 2020
*Advance Resettlement Action Plan to substantial completion* Q1 2021
*Target production commencement* H1 2023Following release of the Feasibility Study and accompanying NI43‐101 Technical Report (ASX/TSX Press Release dated 28 October and 28 November 2019 respectively) the gold price has traded within the range of US$1,492 to US$1,902 per ounce on 24 July 2020. The three-year running average to 24 July 2020 is US$1,385 per ounce.*Project Economic Outcomes*

The Feasibility Study evaluated the Namdini project outcomes at a gold price of US$1,350 per ounce, but also presented gold price sensitivities from US$1,150 per ounce and up to US$1,550 per ounce which Cardinal has set out below in Table 2 below.

*Table 2 – Namdini Project Feasibility Study Outcomes *
*(ASX/TSX Press Release dated 28 October and 28 November 2019 respectively)*

*Project Financial Model*
*Gold Price* *US$ / oz* *1,150* *1,350* *1,550*
Capital Cost
(including $42M contingency) US$M 390 390 *390*
All in Sustaining Costs (AISC)*^1*


Starter Pit  


US$ / oz  


585  


585  


*585*
Life of Mine (15 years) US$ / oz 895 895 *895*
Total Project Payback months 33 21 *9*
Pre‐Tax NPV^5% US$M 406 914 *1,438*
Pre‐Tax IRR % 26 43 *57*Royalties calculated at a rate of 5.5% at UD$1,350/oz and 6.0% at US$1,550/oz and a corporate tax rate of 32.5%; both subject to negotiation.*^1* Cash Costs + Royalties + Levies + Life of Mine Sustaining Capital Costs (World Gold Council Standard).

The forecast financial information set out above in Table 2 was initially contained in Cardinal’s Feasibility Study (refer Cardinal’s ASX Announcement dated October 28, 2019 titled “Feasibility Study Confirms Namdini as Tier One Gold Project”.) Cardinal confirms that all the material assumptions underpinning the above forecast financial information in the Feasibility Study continue to apply and have not materially changed.

**Project Development Partners **

**Table 3: FEED Team:**

*COMPANY* *ROLE*
Lycopodium Feasibility Study Managers. Process plant and associated
infrastructure. Capital and Process Operating cost estimation.
AMC Consulting Mine design, planning, optimization, scheduling and mining contractor tendering
Orway Minerals Consultants Comminution data analysis, crushing and grinding option
studies.
ALS Laboratory (Perth) Metallurgical test work to support the process design criteria.
Knight Piésold Consulting Tailings Storage Facility and selected infrastructure design.
Independent Metallurgical Operations Metallurgical test work management and analysis
MPR Geological Consultants Mineral Resource modelling of the Namdini Deposit.
Orefind Geology and deposit structural genesis.
Sebbag Group International Mine Design Management and Review.
NEMAS Consult & Geosystems Consulting Environmental Impact Assessment Study.
Whittle Consulting Enterprise Optimization of the Namdini Project.
Alastri Software Tactical Scheduling, Haulage Modelling and Reserving
Software.
Maelgwyn Mineral Services Africa Aachen^TM process metallurgical optimization.
BDO Advisory Financial Model Integrity & Reviewer (PEA, PFS and FS).
MKM Social Socio‐Economic Study and Resettlement Action Plan.

** ***Project Permits and Approval Status*

· July 2018 – Environmental Impact Statement (“*EIS”*) development and documentation process initiated· December 2019 ‐ Cardinal submitted its Draft EIS for development of the Namdini Project with Ghanaian EPA· January 2020 ‐ Ghanaian Environmental Protection Agency (“*EPA”*) completed its review of the Draft Environmental Impact Statement (EIS) for the development of the Namdini Project. The EIS revised as needed and re‐submitted in March 2020· February 2020 ‐ Relocation Action Plan (*“RAP”*) approved. The RAP was developed over an extended period, inclusive of extensive consultation with the Project Affected People (“*PAP*”) and several levels of the Government. It was signed off by all PAP and subsequently approved by the Ghanaian Minerals Commission· February 2020 ‐ Water License granted. Permits the use of water for construction and mine operations purposes· April 2020 ‐ Ghanaian EPA approves Cardinal’s EIS, granting its Permit for the development of the Namdini Gold Project· July 2020 – The Namdini Mining Licence had officially received Sovereign Parliamentary Ratification in Ghana

The Company was granted an environmental permit for the Namdini Gold Project by EPA on April 20, 2020. The permit expires October 20, 2021. Renewal is expected on October 27, 2021 following the submission of an Environmental Management Plan (*“EMP”*). The EMP will be submitted six months prior to the expiry.

Developing a safe, successful, and sustainable gold mine continues to be a principal focus for Cardinal Resources. Progress on permitting initiatives are as follows:

· Application for Bulk Oil Facility permit from the Ghana EPA· Registration of the proposed Environmental Impact study with the EPA· Application for zoning letter from the Talensi District Assembly

Outlook for the third quarter is as follows:

· Application for Fire Certificate from the Ghana National Fire Service· Rehabilitate existing access road to the project site· Application for chemical use permit from the EPA and Narcotics Board of Ghana· Create access to proposed water abstraction point on the White Volta· Implement operations Health, Safety and Environmental (HSE) Management System· Application for mine operating permit from the Minerals Commission of Ghana

*Resettlement Action Plan*

MinCom has approved Cardinal’s RAP for its Namdini Gold Project in the Talensi District of the Upper East Region of Ghana, West Africa. The RAP report was produced in accordance with the Minerals and Mining (Compensation and Resettlement) Regulation 2012 (L.I 2175), and International Finance Corporation’s (“*IFC”*) Performance Standards on Social and Environmental Sustainability.

MinCom’s approval has paved the way for construction of 275 structures including residential and public buildings for the people of Accra Site and Buing village, which is planned for the next financial year. The 270 impacted households with a total population of 1,410 people will be compensated for loss of assets and livelihood. Existing infrastructure will be improved. The communities signed the Resettlement Agreement with the Company on February 11, 2020.

*FEED Update*

All works for the FEED programme were wound down for Cardinal’s appointed consultants following advice from the Company due to the global spread of COVID‐19.

Additional land was acquired for the Namdini project area which resulted in the tailings storage facility (*“TSF”*), water storage facility (*“WSF”*) and waste storage dump (*“WSD”*) being optimised with the additional space being made available.

A summary of the FEED activities up to the point of suspension were as follows:

· Cardinal continued negotiating the separable Engineering Procurement and Construction Management contracts with Lycopodium· The following design notices were being processed:

° An 11kV power supply selected for the river abstraction pumps as opposed to a diesel generator set

° Splitting of the oxygen demand into two separable oxygen plants for redundancy

° Specifications of the lease boundary fencing to be upgraded.

° A carbon-in-leach (“*CIL*”) tower crane chosen as opposed to a gantry crane

° Addition of a semi‐automatic Sodium Metabisulphite handling system

° Addition of a Lime Blower for delivery to the Process Plant outside of the Plant fence

° Haul truck crossovers for tailings and decant pipelines

° Flat pack versus block work for the permanent accommodation camp, fly camp and construction camp

° Reducing the size and hence cost of the primary crusher· The site lay-out issued for final review· The Project Execution Plan in the process of being reviewed by Cardinal· An updated TSF dam breakage analysis completed and issued to Cardinal· The WSF relocated and a new WSD designed.

The project execution schedule was premised on a Financial Investment Decision (“*FID*”) date of May 1, 2020 and a site access date of September 1, 2020. At the time of suspension, the schedule was ready for review by Cardinal.

Specific schedule target milestones are defined as follows:

· Plant warehouse to be commissioned and handed over 12 months before first gold pour· Incinerator to be commissioned and handed over 12 months before first gold pour· Mining Service Area Facility to be commissioned and handed over 9 months before first gold pour· Metallurgical laboratory to be commissioned and handed over 6 months before first gold pour

A constructability project review was completed during the FEED, to be ready for a planned Hazard Identification (“*HAZID*”) analysis. The HAZID was cancelled due to the suspension.

The following procurement packages were in various stages of evaluation:

· Fly Camp Facilities, Operation and Camp Management· Site Survey Services· Infrastructure Bulk Earthworks· Plant Bulk Earthworks· Concrete Works· Field Erected Tanks and Steel Framed Buildings· Construction Camp Services

Mining contract tender expressions of interest were sent to thirteen (13) potential mining contractors.

**Namdini Project Drilling**

**Namdini Infrastructure Sterilisation Drilling**

During the Quarter, sterilisation drilling was suspended.  Sterilisation drilling to date as expected has returned no significant mineralisation.

To date, approximately 37,164m of drilling has been completed, comprising of 381 reverse circulation (“*RC*”) drillholes for approximately 36,529m and 2 diamond drillholes for approximately 635m (Figure 3).

Figure 3 accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/d22a90c0-5fb2-488f-8ffb-390b727284c3

**Namdini Infrastructure Geotechnical Drilling **

No Geotechnical drilling and test-pitting were undertaken for the project infrastructure during the Quarter,  due to the COVID-19 restrictions.  Figure 4 highlights completed Geotech investigations on the TSF and Process Plant areas.

Figure 4 accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/a2fc8424-ae66-43e0-8738-6ca5f0ad3503

*REGIONAL EXPLORATION UPDATE*

The Company owns exploration rights to two exploration projects: The Bolgatanga Project which includes Bongo Licence Area, Kungongo Licence and Ndongo Licence Area (Figures 1 and 5) located in the northeast of Ghana and the Subranum Project located in the southwest of Ghana (Figures 1 and 9).

The main focus of the Company’s regional exploration programme during the Quarter was field mapping and ground-truthing initiated after a review of structures and targets generated from geophysical data, historical RC results and a follow up on identified geophysical targets with trenching and sampling programme at Yameriga (RL9/19) (Figure 5).

Figure 5 accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/ebd95aaf-2bb2-4bb9-884f-442195b600a9

***7.4Mt @ 1.31g/t Au for 0.4Moz Au Proved and 131.2Mt @ 1.12g/t Au for 4.7Moz Au Probable; 0.5g/t Au cut‐off

*BOLGATANGA PROJECT*

**Ndongo Licence Area**

The Ndongo Licence Area, hosts part of the extensive regional Bole-Bolgatanga Fault in the northwest and the prospective Nangodi Shear Zone in the centre of the licence area. The licence area wraps around the southern end of the Palungu granitoid intrusive, in the south-eastern region of the licence and forms the main area of prospectivity on the tenement (Figure 5).

The Ndongo Licence Area, comprises of the combined, Nangodi Prospecting Licence (RL9/13, covering a land size of 84.7km²), Ndongo Prospecting Licence (RL9/22, covering a land area of 157km²), and Yameriga Prospecting Licence (RL9/19, covering a land size of 36.78km²), granted to Cardinal to prospect for gold in the Bolgatanga and Talensi Nabdam District in the Upper East Region in the Republic of Ghana. The combined land area of the Ndongo Licence Area is 278.48km².

The Company focused exploration activities during the Quarter at Yameriga conducting field mapping, ground truthing, trenching and some scout RC drilling after a review of geophysical targets, historical RC results and artisanal workings (Figure 6). Rock chip samples collected from veins in adits and rock dumps around adits in heavily artisanal areas returned significant gold assays. A summary of the highlighted results is shown in Table 5 and in Figure 6 below. The significant assays returned from the rock chip samples indicate the potential for discovery of high-grade economic gold mineralisation at Yameriga and warrant further detailed exploration work. Rock chips were mainly quartz veins (milky and smoky) with iron staining and occasional visible specks of gold. Primary rocks encountered were variably altered volcaniclastics with chlorite-silica alteration and specks of sulphides (Rock Chip sample pictures in Figure 7).

A total of 17 scout RC drillholes totaling 1,070m and 1 DD totaling 49.88m were also completed and dispatched to Intertek Laboratory. Assay results are still pending and will be reported next Quarter. Table 4 lists the drillhole and trenching activity undertaken within the quarter.

*Table 4: Yameriga First Pass RC Drilling and Trenching*

*Programme* *No.
**Holes* *RC*
*(m)* *DD*
*(m)* *Total **(m)* *No.
**Samples* *No.*
*Duplicates* *No.
**Blanks* *No.
**Stds* *Total
**Samples*
*Drilling* 18 1,070 49.88 1,119.88 1,120 52 26 27 1,225
*Trenching* 2 -   34 49 2 1 1 53

*Table 5: Yameriga Rock Chip Samples*

*SampleID* *GridID* *mEast* *mNorth* *mRL* *Au (g/t)*
YMRX047 UTM WGS84 Zone 30 North 743,390 1,185,571 223 129.2
YMRX044 UTM WGS84 Zone 30 North 743,377 1,185,567 225 13.5
YMRX041 UTM WGS84 Zone 30 North 743,388 1,185,564 223 68.4
YMRX019 UTM WGS84 Zone 30 North 743,223 1,185,872 218 28.9
YMRX017 UTM WGS84 Zone 30 North 743,222 1,185,873 218 20.0
R332468 UTM WGS84 Zone 30 North 744,687 1,183,665 119 4.7
R332454 UTM WGS84 Zone 30 North 745,364 1,185,748 179 0.7
R332447 UTM WGS84 Zone 30 North 744,946 1,184,192 232 7.2

Figure 6 accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/4569c4b2-1f52-4698-b95a-45c0d527fea4

Figure 7 accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/96d44b0b-d44a-4e4d-9e24-120f958cebfd

Two follow-up trenches were also completed during the quarter for a total of 34m (Figures 6 and 8). The purpose for the trenching was to obtain a better understanding of the host rocks, styles of mineralisation, structural controls and to ultimately refine targets generated from geophysical surveys. Mapping and sampling (horizontally and vertically) were completed within the saprolite along the trench walls, targeting the two types of veins (milky and smoky) encountered (Figure 8). Trench YMTR002 returned significant gold assays summarised in Table 6.

*Table 6:  Summary of Individual Trench Significant Assays at Yameriga*

*TrenchID* *Azimuth (°)* *GridID* *mEast* *mNorth* *mFrom* *mTo* *mWidth* *Au (g/t)*
YMTR002 170 UTM WGS84
Zone 30 North 743,382 1,185,562 1.0 3.0 2 33.3
YMTR002 170 UTM WGS84
Zone 30 North 743,380 1,185,568 7.0 12.0 5 2.5
YMTR002 170 UTM WGS84
Zone 30 North 743,380 1,185,568 11.0 12.0 1 1.0

Figure 8 accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/b57b6390-3286-4ddf-a7f4-d6caf418cb80

**Kungongo Licence Area**

The Kungongo Prospecting Licence (RL9/28) is located approximately 40km west of Namdini Gold Project and covers a total land size of 122.4km². The licence hosts the extensive regional Bole-Bolgatanga fault over a length of 6km in the northwest corner of the tenement. The tenement is underlain by Birimian greenstones which have been extensively intruded by younger granitoids (Figure 5).

As part of the Company’s precautionary measures put in place to minimize the risk of exposure of employees amid the COVID-19 pandemic, all exploration activity at Kungongo was placed on hold during the Quarter.

**Bongo Licence Area**

The Bongo Licence Area covers a total land area of 465km². It hosts part of the regional Bole-Bolgatanga Fault (Figure 5).

The Bongo Licence Area comprises of the combined, Bongo Prospecting Licence (PL9/29 covering a land size of 155km²) located in the Bongo area, Kandiga-Atibisi Prospecting Licence (PL9/38 covering a land size of 155km²) located in the Kandiga-Atibabisi area,  and Zoko-Tarongo Prospecting Licence (PL9/37 covering a land size of 155km²) located in the Zoko-Tarongo area all in the Upper East region of Ghana.

As part of the precautionary measures put in place by the Company to minimize the risk of exposure of employees amid the COVID-19 pandemic, the Company suspended all exploration activity  at the Bongo Licence Area  during the Quarter.

**SUBRANUM PROJECT**

The Subranum Project covers an area of 71.4km² located in southwest Ghana. The license straddles the eastern margin of the Sefwi Gold Belt which is bounded by the regional Bibiani Shear Zone (“*BSZ”*) stretching about 200km across southwestern Ghana (Figure 9).

There is 9km of the BSZ developed within the Subranum license trending NE to SW. The BSZ forms a very prospective, sheared contact between Birimian phyllites and greywackes to the southeast and mafic to intermediate volcanics and volcaniclastics to the northwest. Granitoid stocks of the Dixcove suite intrude this shear zone.

The portion of the Bibiani Shear Zone occurring within the Subranum tenement is 9km long, trending SW to NE. Previous extensive exploration has outlined a 5km long gold target, extending from the SW tenement boundary towards the NE, with the remaining 4km of the 9km strike length remaining relatively unexplored.

All exploration activities were on hold during this Quarter as part of the Company’s precautionary measures to minimize the risk of exposure of employees to COVID-19.

Figure 9 accompanying this announcement is available at https://www.globenewswire.com/NewsRoom/AttachmentNg/98eb17ce-37aa-4e3d-854d-8927a98ec9bf

*TENEMENT SCHEDULE ‐ ASX LISTING RULE 5.3.3*

The following tenement information is provided pursuant to ASX Listing Rule 5.3.3. No tenements in part or whole were relinquished, surrendered or otherwise divested during the Quarter ended June 30, 2020.

All Cardinal’s tenements are in good standing with the Ghanaian Minerals Commission.

*Project* *Licence*
*Area* *Tenement*
*Name* *Tenement*
*Number* *Licence*
*Type* *Interest
Acquired
During
Quarter* *Interest
Divested
During
Quarter* *Interest Held
at End of
Quarter*
* *   Bongo RL9/29 Prospecting - - 100 %
* * Bongo Kandiga-Atibabisi PL9/38 Prospecting - - 100 %
*Bolgatanga*   Zoko-Tarongo PL9/37 Prospecting - - 100 %   Nangodi PL9/13 Prospecting - - 100 % Ndongo Ndongo PL9/22 Prospecting - - 100 %   Yameriga RL9/19 Prospecting - - 100 % Kungongo Kungongo RL9/28 Prospecting - - 100 %
*Namdini* Namdini Datoko PL9/29 Mining Lease - - 100 %
*Subranum* Subranum Subin-Kaso PL9/309 Prospecting - - 100 %

**CORPORATE UPDATE**

**Finance Update**

The Company announced that the senior secured credit facility (as amended in February 2020 and March 2020) (“*Facility*”) had been assigned from Sprott Private Resource Lending L.P. (“*Sprott*”) to the Ghana Infrastructure Investment Fund (“*GIIF*”), a Ghana Government owned infrastructure investment vehicle.

As a result of the acquisition, Cardinal’s senior debt facility provider is now GIIF.

The balance of the Facility was approximately US$23.8 million (following a US$0.4 million repayment of the debt to Sprott prior to the transaction) and Cardinal has also been provided with further funding (from previously restricted cash) totaling an additional US$3.1 million which now forms part of Cardinal’s working capital.  As part of the transaction, Cardinal agreed to amend and restate the Facility under Ghanaian law.

The material commercial terms of the Facility (below) remain unchanged or are otherwise more favourable for Cardinal, as set out below:

· 24-month repayment term (the Sprott arrangements had a maturity date of March 1, 2021)
· Interest rate of 7.75% + the greater of 3 months LIBOR or 1% per annum
· Early repayment flexibility is continued and as per the arrangements with Sprott, a 5% redemption premium applies to all future repayments of the Facility
· Secured against the assets of Cardinal and its wholly owned subsidiaries in Ghana
· Upon a change of control of Cardinal, GIIF may require repayment of the Facility (under the prior Sprott arrangements, immediate repayment was required in such circumstances)

*Corporate Update*

*NordGold Bid*

On March 16, 2020 the Company advised that it has received notification from Nord Gold SE (“*Nordgold”*) that it had acquired a relevant interest of 19.9% in shares of Cardinal, (having acquired the 16.4% stake previously owned by Goldfields Limited), and further advised that Nordgold had provided a non-binding indicative and conditional proposal to acquire all of the issued capital of Cardinal that it did not already own for $A0.45775 per share in cash (*“Nordgold Bid”*).

*Shandong Offer*

On June 18, the Company announced that it had entered into a Bid Implementation Agreement with Shandong Gold Mining (Hong Kong) Co, Ltd (a subsidiary of Shandong Gold Mining Co, Ltd), pursuant to which Shandong Gold had agreed to acquire 100% of the issued and outstanding ordinary shares in Cardinal at a price of A$0.60 cash per share, by way of an off-market takeover offer.

Cardinal’s Board of Directors carefully considered the Shandong Gold Offer in consultation with the Special Committee appointed in connection with the strategic process. Accordingly, Cardinal’s Board of Directors unanimously recommended that all Cardinal shareholders accept the Shandong Gold Offer in the absence of a superior proposal.

Cardinal’s Directors, who collectively hold approximately 6.37% of Cardinal’s ordinary shares, intend to accept the Shandong Gold Offer in respect of all Cardinal shares they own or control by the later of 21 days after the offer is opened for acceptance and 5 days after dispatch of the Cardinal Target’s Statement, in the absence of a superior proposal.

Cardinal’s Board of Directors have been exploring a range of potential transactions to maximise value for shareholders and consider that the Shandong Gold Offer as the best option for shareholders, in the absence of a superior proposal, and will deliver several key benefits to shareholders including:

· *Certain and immediate value for Cardinal shareholders* - ability for shareholders to realize certain and immediate value at a significant premium to Cardinal’s trading price on the ASX and TSX markets. By accepting the Shandong Gold Offer, subject to the Shandong Gold Offer going unconditional, Cardinal shareholders will receive cash consideration of A$0.60 for every Cardinal share they own· *No financing condition* - the Shandong Gold Offer is an all-cash offer and is not subject to any financing conditions· *Avoids risks associated with mine development* – the Shandong Gold Offer eliminates exposure to the risks inherent in any new mine development, including financing, operational and regulatory risks

Subsequent to the quarter end the Company issued 26,000,000 fully paid ordinary shares to Shandong Gold to raise AU$11.96 million in accordance with the BIA. Shareholder approval was not required for this Placement as the Company issued the shares under its Listing Rule 7.1 placement capacity.

The funds raised by the Placement will be used to ensure Cardinal may continue advancing the Namdini Project towards development and working capital.

*Revised Nordgold Bid*

On July 15, 2020 the Company received an unconditional on-market takeover offer for Cardinal at AU$0.66 cash per share from Nordgold (“*Revised Nordgold Bid”*).

Cardinal also noted that as the Nordgold Takeover Bid was unsolicited, it will need to be considered in detail by the Board, together with the Special Purpose Committee and its financial and legal advisers.

*Revised Shandong Gold Offer*

On July 27, 2020 Cardinal announced that the Company had received a revised and improved proposal for an off-market takeover offer from Shandong Gold pursuant to which Shandong Gold will offer to acquire all of the shares in Cardinal it does not presently own at a cash price of A$0.70 per Share (the “*Revised Shandong Gold Offer*”). 

After careful consideration of the Revised Shandong Gold Offer and Revised Nordgold Bid, Cardinal’s Board of Directors (in consultation with the Special Committee, its financial and legal advisors), unanimously recommend that Cardinal shareholders:

· *ACCEPT* the Revised Shandong Gold Offer (in the absence of a superior proposal); and· *REJECT* the Revised Nordgold Bid.

The recommended Revised Shandong Gold Offer of A$0.70 cash per share values Cardinal at approximately A$395 million on a fully diluted basis and represents an attractive premium of approximately 6.1% to the Revised Nordgold Bid of A$0.66 cash per share announced on 15 July 2020.

The Board of Directors considered the Revised Nordgold Bid closely and in the context of the Revised Shandong Gold Offer and took into account, amongst other matters, the price and conditionality of the two offers.

Whilst the Board acknowledges that the Revised Nordgold Bid is unconditional, based on the information available to it at the date of this announcement, the Board has no reason to believe the conditions of the Revised Shandong Gold Offer (which include, amongst other conditions, 50.1% minimum acceptance by Cardinal shareholders and Foreign Investment Review Board (FIRB) approval), cannot be satisfied within a reasonable timeframe.  Cardinal understands that Shandong Gold has received all necessary Chinese regulatory approvals, with the result that the Revised Shandong Gold Offer is no longer conditional on any Chinese regulatory approvals.

The Board also notes that there is the potential for certain shareholders to be aggrieved by the structure of the Revised Nordgold Bid (namely those Shareholders holding Cardinal Shares in non-Australian depositaries or on branch registers).  While the Revised Nordgold Bidder’s Statement alludes to a practical mechanism whereby such Cardinal Shares can be moved to an Issuer Sponsored Holding or CHESS Holding in Australia in order to accept the Revised Nordgold Bid, it is possible that the Revised Nordgold Bid could be subject to regulatory issues (particularly in Canada) which could result in it being prevented from proceeding in the absence of corrective steps taken by Nordgold.

As the Directors have determined to continue to unanimously recommend that Cardinal Shareholders accept the Shandong Gold Offer (in the absence of a Superior Proposal), the Bid Implementation Agreement requires Cardinal and Shandong Gold to use their best endeavours to agree any amendments to the Bid Implementation Agreement which are reasonably necessary or desirable to reflect the revised and improved Shandong Gold Offer. Cardinal anticipates entering into an appropriate amending agreement to give effect to such amendments imminently.

Cardinal announced on 30 July 2020 that it had entered into a deed with each of Shandong Gold Mining (HongKong) Co., Limited and Shandong Gold Mining Co., Ltd, to amend the Bid Implementation Agreement (“*Deed*”).

In summary, the Deed amends the BIA to, amongst other matters:
- increase the Offer Price to A$0.70 per Share;
- note that the Offer will no longer be subject to any Chinese regulatory approvals;
- make certain changes to the proposed timetable of the Offer;
- increase the ascribed value per Cardinal Option for certain Options; and
- increase the break fee so that it continues to represent approximately 1% of the deal value.

Cardinal’s joint financial advisors are Maxit Capital LP (Nth America), Hartleys Limited (Australia), Cannacord Genuity Corp. and BMO Capital Markets and its legal advisors are HopgoodGanim Lawyers (Australia) and Bennett Jones LLP (Canada).

*Timetable and Next Steps*

Detailed information relating to the Revised Shandong Gold Offer will be set out in the Bidder’s Statement and Target’s Statement, which are now expected to be dispatched to Cardinal shareholders on or about 13 August 2020.  The Bidder’s Statement and Target’s Statement will set out important information, including how to accept the Revised Shandong Gold Offer, information about Shandong Gold and the key reasons as to why Cardinal Shareholders should accept the Revised Shandong Gold Offer (in the absence of a Superior Proposal).

**CAPITAL STRUCTURE**

As at July 30, 2020 the Company had the following capital structure:

Capital Structure Listed Unlisted Total
Fully Paid Ordinary Shares (CDV) 526,024,522 ‐ 526,024,522
Unlisted Options Ex. $0.75 on or before 21 Dec 2022 ‐ 1,000,000 1,000,000
Milestone Options Ex. $0.50 on or before 12 Apr 2022 ‐ 18,500,000 18,500,000
Milestone Options Ex. $0.965 on or before 21 Dec 2022 ‐ 2,018,100 2,018,100
Milestone Options Ex. $0.679 on or before 21 Dec 2022 ‐ 2,180,049 2,180,049
Milestone Options Ex. $0.59 on or before 21 Dec 2022 ‐ 2,180,049 2,180,049
Unlisted Options Ex. $1.00 on or before 21 Dec 2022 ‐ 1,867,817 1,867,817
Unlisted Milestone Options Ex on or before 10 Dec 2024 ‐ 6,369,557 6,369,557
Unlisted Milestone Options Ex on or before 10 Dec 2024 ‐ 5,476,530 5,475,530

**Cash Balance**

The Company’s cash balance at June 30, 2020 was approximately AU$3.7 million, subsequent to the quarter end the Company raised AU$11.6 million.

*APPENDIX 5B*

Cardinal Resources Limited provides the following information in relation to payments to related parties and their associates, as required by 6.1 and 6.2 for the 30 June 2020 2020 Appendix 5B.

HopgoodGanim Lawyers of which Michele Muscillo, a Non-Executive Director, is a partner of, provided legal services to the Company. Amounts that have been paid or payable total AU$370,248 for the three months ended June 30, 2020.

During the Quarter ended June 30, 2020 a total of AU$244,722 was paid to all Directors’ of the Company as remuneration.

**ABOUT CARDINAL**

Cardinal Resources Limited (ASX/TSX: CDV) is a West African gold‐focused exploration and development Company that holds interests in tenements within Ghana, West Africa.

The Company is focused on the development of the Namdini Gold Project and released its Feasibility Study on 28 October 2019. 

Cardinal confirms that it is not aware of any new information or data that materially affects the information included in its announcement of the Ore Reserve of October 15, 2019.  All material assumptions and technical parameters underpinning this estimate continue to apply and have not materially changed.

The Namdini Project has a published gold *Ore Reserve of 5.1Moz *(138.6Mt @ 1.13g/t Au; 0.5g/t cut‐off), inclusive of 0.4Moz Proved (7.4Mt @ 1.31g/t Au; 0.5g/t cut‐off) and 4.7Moz Probable (131.2Mt @ 1.12g/t Au; 0.5g/t cut‐off).

Authorized for release by the Board of Cardinal Resources Limited.

For further information contact:    
*Archie Koimtsidis*   *Alec Rowlands*
*CEO / MD*   *IR / Corp Dev*
*Cardinal Resources Limited *   *Cardinal Resources Limited*
*P: +61 8 6558 0573*   *P: +1 647 256 1922*    
*Cannings Purple (Investor Relations, Australia)*
*Peta Baldwin or Warrick Hazeldine*
*E: *pbaldwin@canningspurple.com.au* E: *whazeldine@canningspurple.com.au

*Competent / Qualified Person Statement
*The information in this press release that relates to Exploration Results is based on information prepared by Mr. Paul Abbott, a full-time employee of Cardinal Resources, who is a member of the Geological Society of South Africa. Mr. Abbott has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and the activity which he is undertaking to qualify as a Competent Person, as defined in the 2012 Edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves”.

The scientific and technical information in this announcement that relates to Exploration Results, Mineral Resources and Ore Reserves at the Namdini Gold Project has been reviewed and approved by Mr. Richard Bray, a Registered Professional Geologist with the Australian Institute of Geoscientists and Mr. Ekow Taylor, a Chartered Professional Geologist with the Australasian Institute of Mining and Metallurgy. Mr. Bray and Mr. Taylor have more than five years’ experience relevant to the styles of mineralisation and type of deposits under consideration and to the activity which is being undertaken to qualify as a Competent Person, as defined in the 2012 Edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves” and as a Qualified Person for the purposes of NI43‐101. Mr. Bray and Mr. Taylor are full‐time employees of Cardinal and hold equity securities in the Company.

Cardinal confirms that it is not aware of any new information or data that materially affects the information included in its announcement Ore Reserve of 03 April 2019. All material assumptions and technical parameters underpinning this estimate continue to apply and have not materially changed.

*ASX Listing Rule 5.23.2*
This report contains information extracted from the following reports which are available for viewing on the Company’s website www.cardinalresources.com.au :

· 4 May 2020             Cardinal Company Update
· 30 Mar 2020            Company Update
· 26 Mar 2020            Cardinal Expands Namdini Mining Licence Area
· 11 Mar 2020            Cardinal Receives Approval for Resettlement Action Plan
· 27 Feb 2020            Cardinal Receives Key Water Extraction Permits
· 31 Jan 2020            31 Dec 2019 Quarterly Activities and Cashflow Report
· 29 Jan 2020            Namdini Project Finance Update
· 28 Nov 2019           Cardinal Files Feasibility Study NI 43‐101 Technical Report
· 31 Oct 2019            Sep 2019 Quarterly Activities and Cashflow Report
· 28 Oct 2019            Feasibility Study Confirms Namdini as Tier One Gold Project
· 15 Oct 2019            Mineral Resource and Ore Reserve Statement
· 30 Sept 2019          Feasibility Study Update
· 16 July 2019           Cardinal’s Starter Pit Infill Drilling Results
· 10 July 2019           Cardinal Reports Further Shallow High‐Grade Gold
· 04 June 2019          Positive Metallurgical Update on the Namdini Project
· 18 April 2019          Addendum to Namdini Ore Reserve Press Release
· 03 April 2019          Cardinal’s Namdini Ore Reserve Now 5.1 Moz
· 27 Mar 2019           Cardinal Intercepts High‐Grade Shallow Gold at Ndongo East
· 23 Jan 2019            Cardinal Hits More High‐Grade Shallow Gold at Ndongo East
· 28 Nov 2018           New Drill Season hits high‐grade shallow gold at Ndongo East
· 29 Aug 2018           Cardinal Extends Ndongo East Discovery Strike Length
· 16 July 2018           Cardinal Makes New Gold Discovery at Ndongo East
· 28 May 2018           Encouraging First Pass Gold Results at Ndongo

The Company confirms it is not aware of any new information or data that materially affects the information included in this report relating to exploration activities and all material assumptions and technical parameters underpinning the exploration activities in those market announcements continue to apply and have not been changed. The Company confirms that the form and context in which the Competent Person’s findings are presented have not been materially modified from the original market announcements. Cardinal is not aware of any new information or data that materially affects the information included in its announcement of the Ore Reserve of October 15, 2019. All material assumptions and technical parameters underpinning this estimate continue to apply and have not materially changed.

*Disclaimer*

This ASX / TSX press release has been prepared by Cardinal Resources Limited (ABN: 56 147 325 620) (“Cardinal” or “the Company”). Neither the ASX or the TSX, nor their regulation service providers accept responsibility for the adequacy or accuracy of this press release.
This press release contains summary information about Cardinal, its subsidiaries and their activities, which is current as at the date of this press release. The information in this press release is of a general nature and does not purport to be complete nor does it contain all the information, which a prospective investor may require in evaluating a possible investment in Cardinal.

By its very nature exploration for minerals is a high‐risk business and is not suitable for certain investors. Cardinal’s securities are speculative. Potential investors should consult their stockbroker or financial advisor. There are a number of risks, both specific to Cardinal and of a general nature which may affect the future operating and financial performance of Cardinal and the value of an investment in Cardinal including but not limited to economic conditions, stock market fluctuations, gold price movements, regional infrastructure constraints, timing of approvals from relevant authorities, regulatory risks, operational risks and reliance on key personnel and foreign currency fluctuations.

Except for statutory liability which cannot be excluded and subject to applicable law, each of Cardinal’s officers, employees and advisors expressly disclaim any responsibility for the accuracy or completeness of the material contained in this press release and excludes all liability whatsoever (including in negligence) for any loss or damage which may be suffered by any person as a consequence of any information in this Announcement or any error or omission here from. Except as required by applicable law, the Company is under no obligation to update any person regarding any inaccuracy, omission or change in information in this press release or any other information made available to a person nor any obligation to furnish the person with any further information. Recipients of this press release should make their own independent assessment and determination as to the Company’s prospects, its business, assets and liabilities as well as the matters covered in this press release.

*Forward‐looking statements*

Certain statements contained in this press release, including information as to the future financial or operating performance of Cardinal and its projects may also include statements which are ‘forward‐looking statements’ that may include, amongst other things, statements regarding targets, anticipated timing of the feasibility study (FS) on the Namdini project, estimates and assumptions in respect of Mineral Resources and anticipated grades and recovery rates, production and prices, recovery costs and results, capital expenditures and are or may be based on assumptions and estimates related to future technical, economic, market, political, social and other conditions. These ‘forward – looking statements’ are necessarily based upon a number of estimates and assumptions that, while considered reasonable by Cardinal, are inherently subject to significant technical, business, economic, competitive, political and social uncertainties and contingencies and involve known and unknown risks and uncertainties that could cause actual events or results to differ materially from estimated or anticipated events or results reflected in such forward‐looking statements.
Cardinal disclaims any intent or obligation to update publicly or release any revisions to any forward‐looking statements, whether as a result of new information, future events, circumstances or results or otherwise after today’s date or to reflect the occurrence of unanticipated events, other than required by the Corporations Act and ASX and TSX Listing Rules. The words ‘believe’, ‘expect’, ‘anticipate’, ‘indicate’, ‘contemplate’, ‘target’, ‘plan’, ‘intends’, ‘continue’, ‘budget’, ‘estimate’, ‘may’, ‘will’, ‘schedule’ and similar expressions identify forward‐looking statements.

All forward‐looking statements made in this press release are qualified by the foregoing cautionary statements. Investors are cautioned that forward‐looking statements are not guarantees of future performance and accordingly investors are cautioned not to put undue reliance on forward‐looking statements due to the inherent uncertainty therein.

**SCHEDULE* *1**

*YAMERIGA PROSPECTING LICENCE SURFACE SAMPLING, TRENCH SAMPLING AND DRILL RESULTS*

*HoleID* *Depth (m)* *Dip (°)* *Azimuth (°)* *GridID* *mEast* *mNorth* *mRL*
YMDD003 38 -50 85 UTM WGS84 Zone 30 North 743,207 1,185,869 218
YMRC001 85 -50 85 UTM WGS84 Zone 30 North 743,206 1,185,817 218
YMRC002 85 -50 85 UTM WGS84 Zone 30 North 743,184 1,185,866 216
YMRC003 32 -50 85 UTM WGS84 Zone 30 North 743,199 1,185,918 216
YMRC004 72 -50 85 UTM WGS84 Zone 30 North 743,215 1,185,768 216
YMRC005 66 -50 85 UTM WGS84 Zone 30 North 743,209 1,185,889 216
YMRC006 20 -50 85 UTM WGS84 Zone 30 North 743,217 1,185,871 216
YMRC007 36 -50 260 UTM WGS84 Zone 30 North 743,229 1,185,872 216
YMRC008 74 -50 122 UTM WGS84 Zone 30 North 743,523 1,186,210 230
YMRC009 54 -50 80 UTM WGS84 Zone 30 North 743,372 1,185,566 220
YMRC010 54 -50 80 UTM WGS84 Zone 30 North 743,385 1,185,518 222
YMRC011 60 -50 80 UTM WGS84 Zone 30 North 743,373 1,185,616 221
YMRC012 50 -50 28 UTM WGS84 Zone 30 North 743,377 1,185,544 224
YMRC013 50 -50 28 UTM WGS84 Zone 30 North 743,360 1,185,565 221
YMRC014 50 -50 28 UTM WGS84 Zone 30 North 743,403 1,185,540 221
YMRC015 85 -50 123 UTM WGS84 Zone 30 North 743,436 1,186,475 224
YMRC016 85 -50 122 UTM WGS84 Zone 30 North 743,572 1,186,175 212

*Meta‐Data* *Listing* *of* *Drill**h**oles*

*TrenchID* *Azimuth (°)* *GridID* *mEast* *mNorth* *mFrom* *mTo* *mWidth* *Au
(g/t)* *Comments*
YMTR002 170 UTM WGS84
Zone 30 North 743,382 1,185,562 1.0 3.0 2 33.3 Vertical sampling
YMTR002 170 UTM WGS84
Zone 30 North 743,380 1,185,568 7.0 8.0 1 11.1 Horizontal sampling
YMTR002 170 UTM WGS84
Zone 30 North 743,380 1,185,568 11.0 12.0 1 1.0 Horizontal sampling

*Summary of Individual Trench Significant Assays*

*SampleID* *GridID* *mEast* *mNorth* *mRL* *Au (g/t)*
YMRX047 UTM WGS84 Zone 30 North 743,390 1,185,571 223 129.2
YMRX044 UTM WGS84 Zone 30 North 743,377 1,185,567 225 13.5
YMRX041 UTM WGS84 Zone 30 North 743,388 1,185,564 223 68.4
YMRX019 UTM WGS84 Zone 30 North 743,223 1,185,872 218 28.9
YMRX017 UTM WGS84 Zone 30 North 743,222 1,185,873 218 20.0
R332468 UTM WGS84 Zone 30 North 744,687 1,183,665 119 4.7
R332454 UTM WGS84 Zone 30 North 745,364 1,185,748 179 0.7
R332447 UTM WGS84 Zone 30 North 744,946 1,184,192 232 7.2

* Summary of Individual Random Rock Chip Samples*

**APPENDIX **

**JORC* *CODE 2012* *EDITION
***TABLE 1 REPORTING OF EXPLORATION RESULTS - YAMERIGA*

*Section 1 – Sampling Technique and Data*

*Criteria* *JORC Code Explanation* *Commentary *
*Sampling techniques* Nature and quality of sampling (e.g. cut channels, random chips, or specific specialised industry standard measurement tools appropriate to the minerals under investigation, such as down hole gamma sondes, or handheld XRF instruments, etc.). These examples should not be taken as limiting the broad meaning of sampling. Random Rock Chip samples comprise of sampling of random surface rocks by collecting rock pieces suitable for assaying. Samples weigh on average 1.5kg. Samples are photographed both wet and dry and geologically logged.

Trench Channel samples comprise of sampling of continuous 1m or 2m interval channel near the base on the entire length of the west face with intervals dictated by observed alterations and mineralisation. Each homogenised sample weighs on the average 2.0kg.

Reverse Circulation (RC) drill samples are collected by using downhole sampling hammers with nominal 140mm diameters. Samples are collected through a cyclone and immediately weighed to determine recoveries; the entire sample is then split by a three‐tier riffle splitter. Two samples (~2.5‐3.0 kg) are collected, one for the laboratory, the other a duplicate stored at the Bolgatanga sample shed.

Diamond drill sampling is by longitudinal half‐core samples of HQ core size.
Include reference to measures taken to ensure sample representivity and the appropriate calibration of any measurement tools or systems used. Sampling is guided by Cardinal Resources protocols and Quality Control procedures as per industry standard.

To ensure representative sampling:
Trench Channel sample tool and sampling site are cleaned between samples and sample material collected over the same interval and volume to ensure representative nature of the samples.

1m RC samples are collected from a cyclone, passing them through a 3‐tier riffle splitter, and taking duplicate samples every 20^th  sample.

HQ core samples are taken selectively through the altered, silicified and shear zones, with minimum 0.5m and maximum 1.5m lengths of sample.
Aspects of the determination of mineralisation that are Material to the Public Report.

In cases where ‘industry standard’ work has been done this would be relatively simple (e.g. ‘reverse circulation drilling was used to obtain 1 m samples from which  3 kg was pulverised to produce a 30 g charge for fire assay’). In other cases, more explanation may be required, such as where there is coarse gold that has inherent sampling problems. Unusual commodities or mineralisation types (e.g. submarine nodules) may warrant disclosure of detailed information. The determination of mineralisation is based on observed alterations, silicification and shearing of the lithologies.

Random Rock Chip, Trench Channel and RC samples are crushed to ‐2mm, then a <1kg split sample is pulverised via LM2 Ring Pulveriser to a nominal 85% passing ‐75µm.

Diamond drill samples are crushed to ‐2mm, and a <1kg split sample is then pulverised via LM2 Ring Pulveriser to a nominal 85% passing ‐75µm.

For Random Rock Chip, RC and Diamond drill samples, a 200g sub‐sample is taken from the pulverised material for analysis. A 50g charge weight is fused with litharge‐based flux, cupelled and the prill dissolved in aqua regia. The gold tenor is then determined by AAS.

For Trench Channel samples, a 1.5kg sub-sample is taken from the pulverised material and gold analysed using Active Cyanide Leach, 24-hour solvent extraction method.
*Drilling techniques* Drill type (e.g. core, reverse circulation, open‐hole hammer, rotary air blast, auger, Bangka, sonic, etc.) and details (e.g. core diameter, triple or standard tube, depth of diamond tails, face‐sampling bit or other type, whether core is oriented and if so, by what method, etc.). Reverse circulation drilling uses sampling hammer of nominal 140mm diameter.

Diamond core drilling is completed with core size of HQ with a standard tube. Triple tube is used in saprolite at the tops of the holes. Core is orientated to determine both azimuth and dip using digital Reflex ACT II RD orientation tool.

Drillholes are inclined at ‐45⁰ to ‐60⁰ angles for optimal zone intersection. All drill collars are surveyed using Trimble R8 RTK GPS with downhole surveying every 30m using Reflex digital surveying instruments.
* * Method of recording and assessing core and chip sample recoveries and results assessed. Diamond core recovery is logged and captured into the database. The method of recording RC Chip and Core sample recoveries was to enter the relevant data on a hand‐held Motion F5te Tablet PC using a set of standard templates supplied by Maxwell Geoservices, Perth (Maxwell).

Reverse circulation sampling is good. RC chips are logged, weighed and captured to the database. RC sample recoveries are assessed by weighing 1m samples from the cyclone on a scale in the field and comparing with the theoretical volume contained in a 1m by 140mm diameter hole to calculate an estimated percentage sample recovery.

Core recovered from each drill run is measured and compared with the drill run length drilled to calculate an estimated percentage core recovery. For core drilling the overall recoveries are excellent with weighted average recovery greater than 98%.
Measures taken to maximise sample recovery and ensure representative nature of the samples. Measures taken include the use of bigger HQ core size diamond drilling to maximise recovery, having a geologist onsite to examine core and core metres marked and orientated to check against the driller’s blocks and ensuring that all core loss is taken into account.
At the reverse circulation rig, sampling systems are routinely cleaned to minimise the opportunity for contamination and drilling methods are focused on sample quality. The measures taken to maximise RC sample recovery are through a cyclone and a 3‐tier riffle splitter. Each 1m sample is passed twice through the splitter before sampling to ensure maximum homogenisation of each sample and to collect an unbiased representative sample to be assayed.

The reverse circulation rigs have auxiliary compressors and boosters to help maintain dry samples. Where wet samples are encountered, the reverse circulation drilling is discontinued.
Whether a relationship exists between sample recovery and grade and whether sample bias may have occurred due to preferential loss/gain of fine/coarse material. No relationship is seen to exist between sample recovery and grade, and no sample bias has occurred due to preferential loss/gain of any fine/coarse material due to the acceptable sample recoveries obtained by the drilling methods employed.
*Logging* Whether core and chip samples have been geologically and geotechnically logged to a level of detail to support appropriate Mineral Resource estimation, mining studies and metallurgical studies. Random Rock Chip samples are fully logged.

All the exposed surfaces along the west trench wall sampled is geologically logged and entered directly to a digital Field Tough book laptop logging system using Cardinal geological codes.

All drillholes are fully logged. The lithology, alteration and geotechnical characteristics of core are logged directly to a digital format on a Field Toughbook laptop logging system following procedures and using Cardinal geologic codes. Data is imported into Cardinal’s central database after validation in LogChief™.

Random Rock Chip and Trench Channel samples are only relevant to early stage exploration and not suitable to support Mineral Resource estimation.

In the opinion of the Component Persons, all geological logging of RC and Core is to a level of detail to support future Mineral Resource estimation.
Whether logging is qualitative or quantitative in nature. Core (or costean, channel, etc.) photography. Logging is both quantitative and qualitative.
All trench exposures are photographed.

Both Random Rock Chip samples, Trench Channel samples, RC chips in trays and HQ core are photographed both in dry and wet form.

The rock outcrop from where the Rock Chip sample was obtained is photographed with co‐ordinates taken; portions of each sample submitted are retained as reference material.
The total length and percentage of the relevant intersections logged. All drill holes are logged in full and to the total length of each drill hole.
*Sub‐sampling techniques and sample preparation* If core, whether cut or sawn and whether quarter, half or all core taken. Orientation of core is completed for all diamond holes and all are marked prior to sampling. Longitudinally cut half core samples are produced using a Core Saw with diamond impregnated blades. Samples are weighed and recorded.
If non‐core, whether riffled, tube sampled, rotary split, etc. and whether sampled wet or dry. RC samples are split using a three‐tier riffle splitter. The majority of RC samples are dry. On occasions that wet samples are encountered, they are dried prior to splitting with a riffle splitter.
For all sample types, the nature, quality and appropriateness of the sample preparation technique. Random Rock Chip samples and Trench Channel samples are dried at 105°C for four hours and weighed. Samples are firstly Jaw Crushed and a second stage crushing is effected through a RSD Jaques crusher to a nominal ‐2 mm and then split to <1.0 kg. The reject sample is retained in the original bag and stored. The split is pulverised in a LM2 Ring Pulveriser to a nominal 85% passing 75µm.

Approximately 200g sub‐sample of the pulverised material of Random Rock Chip sample is used for assay. A 1.5kg sub-sample of the pulverised Trench Channel sample material was used for cyanidation bottle roll analysis for gold.

RC drill samples are sorted and dried in an oven for 8 hours and weighed. They are then crushed to ‐2mm using a RSD Boyd crusher and a <1.0kg split is taken. The reject sample is retained in the original bag and stored. The split is pulverised in a LM2 Ring Pulveriser to a nominal 85% passing 75µm and a 200g sub‐sample is used for analysis.
Drill core samples are sorted, dried at 105°C for 4 hours and weighed. Samples are crushed through Jaques crusher to nominal -10mm. A second stage crushing is through Boyd crusher to nominal -2mm and then split to <1.0kg. The reject sample is retained in the original bag and stored. The split is pulverised in a LM2 Ring Pulveriser to a nominal 85% passing 75%µm and approximately 200g sub‐sample of the pulverised material is used for fire assay.

All preparation equipment is flushed with barren material prior to commencement of the job.
Quality control procedures adopted for all sub‐sampling stages to maximise representivity of samples. Cardinal Resources has protocols that cover the sample preparation at the laboratories and the collection and assessment of data to ensure that accurate steps are used in producing representative samples for the analytical process. Key performance indices include:Contamination index of 95% (that is at least 95% of blanks pass); failures can only be attributed to probable minor laboratory contamination.Crushed Size index of 95% passing 2 mm (1:50 sample screened).Grind Size index of 85% passing 75 microns (minimum 1:50 sample screened).Check Samples returning at worst 20% precision at 90th percentile and bias of 5% or better.

Crusher and pulveriser are flushed with barren material at the start of every batch.
Measures taken to ensure that the sampling is representative of the in‐ situ material collected, including for instance results for field duplicate/second‐half sampling. Measures taken to ensure that the Trench Channel sampling is representative of the in‐situ material collected is to take approximately 2.0kg homogenised samples across the entire 1m or 2m sampling interval.

Me

Full Article