EV (Earned Value) the budgeted value of work actually completed
EV (Earned Value) the budgeted value of work actually completed

I.e.

The amount of money that should be invested in the completed work up to a certain point.ETC (Estimated cost of remaining work) ETC = total PV - EV completed or ETC = PV of remaining work x CPI2) Most common yardsticks CV (Cost deviation) CV = EV - ACCV0 (Cost saving) CV0 (Cost overrun) SV (Schedule deviation).

SV=EV-PVSV0 (over schedule) SV0 (behind schedule)